Wednesday, 14 March 2012


Networking Analysis
Assignment I
Q1.      Draw the network from the following activities and Find Critical Path & Total Project Duration
Activity
A
B
C
D
E
F
G
Immediate Predecessor
-
-
A
A
B
B
D&G
Duration (Days)
10
9
9
8
7
11
5

Q2.      Draw the network from the following activities
Activity
A
B
C
D
E
F
G
H
I
J
K
L
M
Immediate Predecessor
-
A
A
B
A
B
C&D
F
G
G
G
H&I
E&J

Q3.      Draw the network from the following activities
Activity
A
B
C
D
E
F
G
H
I
J
K
L
M
Immediate Predecessor
-
A
A
A
B
C
C
D
F
H
I
EKG
LJ

Q4.      Draw the network from the following activities
Activity
A
B
C
D
E
F
G
H
I
J
K
L
M
Immediate Predecessor
-
-
B
A
C
C
F
F
H
I
DEGJ
I
KL

Q5.      Draw the network from the following activities and Find Critical Path & Total Project Duration
Activity
A
B
C
D
E
F
Immediate Predecessor
-
-
A
A
BC
D
Duration (Days)
12
10
5
6
16
16

Q6.      Draw the network from the following activities and Find Critical Path & Total Project Duration
Activity
A
B
C
D
E
F
G
H
I
J
K
Immediate Predecessor
-
A
B
C
B
E
D&F
E
H
G&I
J
Duration (Days)
13
8
10
9
11
10
8
6
7
14
18

Q7.      Draw the network from the following activities and Find Critical Path & Total Project Duration
Activity
A
B
C
D
E
F
G
H
I
J
Immediate Predecessor
-
A
A
B
B
C
C
D
EF
G
Duration (Days)
3
5
8
4
2
9
3
12
10
6

Q8.      Draw the network from the following activities and Find Critical Path & Total Project Duration
Activity
A
B
C
D
E
F
G
H
I
Immediate Predecessor
-
-
A
A
C
D
B
E&F
G
Duration (Days)
8
6
14
5
11
7
11
4
18

Q9.      Draw the network from the following activities and Find Critical Path & Total Project Duration
Activity
A
B
C
D
E
F
G
H
Immediate Predecessor
-
-
-
A
B
C
DE
FG
Duration (Days)
2
4
3
1
6
5
7
2

Q10.    Draw the network from the following activities
Activity
A
B
C
D
E
F
G
H
I
J
K
L
Immediate Predecessor
-
A
A
A
B
E
C
D
G
D
J
FHI

Q11.    Draw the network from the following activities and Find Critical Path & Total Project Duration
Activity
A
B
C
D
E
F
G
H
Immediate Predecessor
-
-
A
A
B
B
D&E
F&G
Duration (Days)
4
7
3
3
2
2
2
3

Q12.    Draw the network from the following activities and Find Critical Path & Total Project Duration
Activity
A
B
C
D
E
F
G
H
I
J
K
L
Immediate Predecessor
-
A
A
B
C
C
E
F
GH
GH
I
J
Duration
2
4
6
8
6
10
10
14
8
12
4
10

Q13.    Draw the network from the following activities and Find Critical Path & Total Project Duration
Activity
A
B
C
D
E
F
G
H
I
J
K
L
M
N
Immediate Predecessor
-
-
A
C
D
E
E
D
BD
FGHI
J
J
KL
M
Duration
10
24
14
21
14
25
10
20
8
13
4
12
4
4



Q14.    Draw the network from the following activities and Find Critical Path & Total Project Duration
Activity
A
B
C
D
E
F
G
H
Immediate Predecessor
-
-
-
AB
BC
C
D
GEF
Duration
1
2
2
2
4
1
4
8

Q15.    Draw the network from the following activities and Find Critical Path & Total Project Duration
Activity
A
B
C
D
E
F
G
H
I
J
K
L
M
Immediate Predecessor
E
A
B
K
-
E
F
F
F
IL
CGH
D
IL
Duration
5
1
2
14
16
1
2
3
2
3
4
2
2


Q16.    Draw the network from the following activities and Find Critical Path & Total Project Duration
Activity
A
B
C
D
E
F
G
Immediate Predecessor
-
-
-
AB
AB
CDE
CDE
Duration
4
7
6
5
7
6
5

Q17.    Draw the network from the following activities and Find Critical Path & Total Project Duration
Activity
A
B
C
D
E
F
G
H
I
J
K
L
Immediate Predecessor
-
-
-
AB
B
B
FC
B
EH
EH
CDFJ
K
Duration
3
4
2
5
1
3
6
4
4
2
1
5

Q18.    Draw the network from the following activities and Find Critical Path & Total Project Duration
Activity
A
B
C
D
E
F
G
H
I
J
K
L
Immediate Predecessor
-
-
-
C
ABD
ABD
EF
ABD
H
G
G
IJK
Duration
4
3
3
2
1
2
3
3
5
2
4
2

Q19.    Draw the network from the following activities and Find Critical Path & Total Project Duration
Activity
A
B
C
D
E
F
G
H
I
J
Immediate Predecessor
-
-
AB
B
A
C
EF
DF
GH
I
Duration
3
8
4
2
1
7
5
6
8
9



Q20.    Draw the network from the following activities and Find Critical Path & Total Project Duration
Activity
A
B
C
D
E
F
G
H
I
J
K
L
Immediate Predecessor
-
-
-
BC
A
C
E
E
DFH
E
IJ
G
Duration
9
4
7
8
7
5
10
8
6
9
10
2

Q21.    Draw the network from the following activities and Find Critical Path & Total Project Duration
Activity
A
B
C
D
E
F
G
H
I
J
K
L
Immediate Predecessor
-
-
A
BC
D
E
BC
F
FG
HI
B
FGK
Duration
30
7
10
14
10
7
21
7
12
15
30
15

Q22.    Draw the network from the following activities and Find Critical Path & Total Project Duration
Activity
A
B
C
D
E
F
G
Immediate Predecessor
-
A
A
BC
B
DE
D
Duration
3.3
6.7
3.0
11.0
7.7
6.0
4.0

Q23.    Draw the network from the following activities and Find Critical Path & Total Project Duration
Activity
A
B
C
D
E
F
G
H
I
J
K
Immediate Predecessor
-
-
A
B
C
C
CD
FG
E
I
H
Duration
3
8
9
6
10
14
11
10
5
4
1
Q24.    Draw the network from the following activities and Find Critical Path & Total Project Duration
Activity
A
B
C
D
E
F
G
Immediate Predecessor
-
-
B
B
B
E
ADC
Duration
10
8
5
6
8
5
12
Q25.    Draw the network from the following activities and Find Critical Path & Total Project Duration
Activity
A
B
C
D
E
F
Immediate Predecessor
-
A
A
A
CD
BE
Duration
3
5
5
4
2
3
Q26.    Draw the network from the following activities and Find Critical Path & Total Project Duration
Activity
A
B
C
D
E
F
G
Immediate Predecessor
-
A
A
A
BC
CD
EF
Duration
7
4
5
6
7
5
6

Networking Analysis
Assignment II
Q1.      A project has the following activities
Activity
1-2
1-3
1-4
2-5
3-5
4-6
5-6
Duration
3
8
9
6
10
14
11
Required:        1.         Draw the project network
2.                  Find the critical path and total project duration
3.                  Find earliest start time, latest start time earliest finish time and latest finish time
4.                  Find out total float, Head event slack, Free Float, Tail Event slack and independent Float.

Q2.      A project has the following activities
Activity
A
B
C
D
E
F
G
H
I
Immediate Predecessor
-
-
-
A
A
B
C
D
EF
Duration
7.8
20
33
18
20
9
9.8
8
4
Required:        1.         Draw the project network
2          Find the critical path and total project duration
3          Find earliest start time, latest start time earliest finish time and latest finish time
4.         Find out total float, Head event slack, Free Float, Tail Event slack and independent Float.

Q3.      A project has the following activities
Activity
A
B
C
D
E
F
G
H
I
J
K
Immediate Predecessor
-
-
-
A
B
B
C
D
E
FG
HI
Duration
3
2
2
4
4
7
4
2
5
6
3
Required:        1.         Draw the project network
2          Find the critical path and total project duration
3          Find earliest start time, latest start time earliest finish time and latest finish time
4.         Find out total float, Head event slack, Free Float, Tail Event slack and independent Float.

Q4.      For the following data; draw a network, fine the critical path and the slack time after calculating the earliest expected time and the latest allowable
Activity
1-2
1-3
2-4
2-5
2-6
3-7
3-8
4-9
5-9
6-10
7-10
8-11
9-12
10-12
11-13
12-13
Duration
5
8
6
4
4
5
3
1
3
5
4
9
2
4
1
7
Q5.      A small maintenance project consist of the following twelve jobs whose precedence relations are indented with their node numbers.
Job (i-j)
1-2
1-3
1-4
2-3
2-5
2-6
3-7
4-5
5-6
6-7
6-8
7-8
Duration
10
4
6
5
12
9
12
15
6
5
4
7
Required:        1.         Draw an arrow diagram representing the project
2          Find the critical path and total project duration
3          Find earliest start time, latest start time earliest finish time and latest finish time
4.         Find out total float, Head event slack, Free Float, Tail Event slack and independent Float.
Q6.      The monthly maintenance work in a machine shop consist of 10 steps A to J. The interrelationship between them are identified by event number
Step
A
B
C
D
E
F
G
H
I
J
Event number
1-2
2-3
2-4
3-5
3-6
4-6
4-7
5-8
6-8
7-8
Duration
3
5
8
4
2
9
3
12
10
6
Required:        1.         Draw a network
2          Compute early and latest start and finish time for each activity
3          How much slack does activity (3-5), Activity (4-6) and Activity (7-8) have?
4.         Identify the critical path and critical activity
5.         If activity 2-3 takes 8 days instead of 5 days what will be the project completion time?
Q7.      Draw a network diagram from the following activities and find critical path activities
Job
A
B
C
D
E
F
G
H
I
J
K
Immediate Predecessor
-
A
B
C
B
E
DF
E
H
GI
J
Duration
13
8
10
9
11
10
8
6
7
14
18
Q8.      The NRB Company is planning to design, develop and market a new racing cycle. The project is composed of the following activities.
Activity
A
B
C
D
E
F
G
H
I
J
K
L
Immediate Predecessor
-
-
-
C
ABD
ABD
EF
ABD
H
G
G
IJK
Duration
4
3
3
2
1
2
3
3
5
2
4
2
            Construct the network, determine the critical path and the duration of the above project.
Q9       A small project consist of seven activities for which the relevant data are given below
Activity
A
B
C
D
E
F
G
Immediate Predecessor
-
-
-
AB
AB
CDE
CDE
Duration
4
7
6
5
7
6
5
Required         1.         Draw the network and find the project completion time
2.                  Calculable total float for each of the activities
3.                  Draw the time scaled diagram.
Q10.   
 Activity
1-2
1-3
1-4
2-4
2-5
3-6
4-6
5-7
6-7
6-8
7-8
8-9
Duration
4
12
10
8
6
8
10
10
0
8
10
6
With the help of the activities given above draw a network. Determine a critical  path, earliest start time, earliest finish time, latest start time, latest finish time, total float and free float.

Networking Analysis
Assignment III

Q1.      A Project has the followings activities and characteristics
Activity
1-2
1-3
1-4
2-5
3-5
4-6
5-6



Optimistic
2
4
1
5
2
6
4



Most Likely
5
10
7
8
8
9
7



Pessimistic
8
16
13
11
14
12
10



A)                Find expected duration of each activity.
B)                Draw the project network and expected duration of the project.
C)                Find variance of activities on critical path and its standard Deviation
Ans:-   a)         Critical Path 1-3-5-6 & Duration 25
b)                  Variance (3)
Q2.      A Project has the followings activities and characteristics
Activity
1-2
1-3
1-4
2-5
3-5
4-6
5-6



Optimistic
2
6
1
3
2
6
4



Most Likely
5
6
7
9
8
9
7



Pessimistic
8
6
13
15
14
12
10



A)    Find expected duration of each activity and their variance 
B)    Draw the project network and expected duration of the project.
C)    Find variance of activities on critical path and its standard Deviation
Ans:-               Critical Path 1-2-5-6 or 1-3-5-6& Duration 21days
Q3.      A Project has the followings activities and characteristics
Activity
1-2
2-3
2-4
3-5
4-5
4-6
5-7
6-7
7-8
7-9
8-10
9-10
Optimistic
1
1
1
3
2
3
4
6
2
5
1
3
Most Likely
5
3
5
5
4
7
6
8
6
8
3
7
Pessimistic
1.5
2
3
4
3
5
5
7
4
6
2
5
Required :- Construct a PERT Network. Find the critical path and variance for each even. Find the project duration at 95% probability
Ans:-   Critical Path 1-2-4-6-7-9-10 Duration 28 1/6days
            Probability at 95%      X=30.57 days
Q4.      A Project has the followings activities and characteristics
Activity
A
B
C
D
E
F
G
H
I



Preceding
-
-
A
A
C
D
B
EF
G



Optimistic
1
1
1
3
2
3
4
6
2



Most Likely
5
3
5
5
4
7
6
8
6



Pessimistic
1.5
2
3
4
3
5
5
7
4



Required a)     Draw the PERT Network
(b)        Critical Path
            (c)        Prepare Activity Schedule for the Project     
(d)       Find the Probability that the project is completed in 36 weeks
(e)        if the project managers wishes to be 99% sure that the project is completed on June 2001, when should he start the project work.
Ans:-   Critical Path 1-2-4-6-8 (A-C-E-H) Duration 37days and variance of the critical path is 25 days, Z=42.07% ,            X=48.65.

Q5.      Given the data below find the following (i) The expected task times and their variance (ii) The earliest and latest expected time to reach each node:
Activity
A
B
C
D
E
F
G
H
I
J
K

Least time
4
5
8
2
4
6
8
5
3
5
6

Greatest time
8
10
12
7
10
15
16
9
7
11
13

Most Likely time
5
7
11
3
7
9
12
6
5
8
9

Precedence relationship : A,C,D can start immediately; (E>B,C; FG>D; HI>EF; J>I,G; K>H; B>A)
Sign > is to be interpreted as “depends upon” also draw the network and critical path.
Ans:-   Critical Path 1-2-3-5-7-8 (A-B-E-H-K) Duration 35days

Q6.      A project consist of activity A,B,C,D,_ _ _ H,I. The notation X<Y mean that the activity X must be completed before Y can start & X,Y<W means that W will start only after the completion of activities X&Y with this notation.
a)         Construct the network diagram for the following constraints
            A<D, A<E, B<F, C<G, D<HE, F<I
            The project has the following time schedule of the above activities
Task
A
B
C
D
E
F
G
H
I
Least time
5
18
26
16
15
6
7
7
3
Greatest time
10
22
40
20
25
12
12
9
5
Most Likely time
8
20
33
18
20
9
10
8
4

b)         Determine the following         1. Expected task time and their variance
2.         Earliest and latest expected time to reach each node   3.       Critical Path    4. The Probability of a node occurring at the proposed completion date if the original contract time of completing the project is 41.5 weeks.
Ans:     Critical path 1-4-7 (C-G)  42.80 days