Transportation Problems
Assignment II (Part – A)
Q1. Solve the following Transportation Problem
by NWCM and test its optimality by Stepping Stone Method. The Shipping
Costs are given in the table.
Plants
|
Projects
|
||||
|
A
|
B
|
C
|
Supply
|
|
W
|
4
|
8
|
8
|
56
|
|
X
|
16
|
24
|
16
|
82
|
|
Y
|
8
|
16
|
24
|
77
|
|
Demand
|
72
|
102
|
41
|
215
|
Answer: WB=56, XB=41, XC=41, YA=72,
YB=05. Total Cost= 2744
Q2. Solve the following Transportation Problem
whose cost matrix, availability at each plant & requirement at each
warehouse are given. Apply Stepping Stone Method for optimal solution The Shipping Costs are
given in the table.
|
W1
|
W2
|
W3
|
W4
|
Supply
|
P1
|
15
|
24
|
11
|
12
|
5000
|
P2
|
25
|
20
|
14
|
16
|
4000
|
P3
|
12
|
12
|
22
|
13
|
7000
|
Demand
|
3000
|
2500
|
3500
|
4000
|
16000
13000
|
Answer: P1W3=2500,
P1W4=2500, P2W3=1000, P2W5=3000.P3W1=3000P3W2=2500P3W4=1500 Total Cost= 1,57,000
Q3. Given below is a table. Solve it as
transportation problems & test it optimality. Apply stepping stone method
Factories
|
|
Centers
|
||||
C1
|
C2
|
C3
|
C4
|
Supply
|
||
A
|
10
|
8
|
7
|
12
|
500
|
|
B
|
12
|
13
|
6
|
10
|
500
|
|
C
|
8
|
10
|
12
|
14
|
900
|
|
Demand
|
700
|
550
|
450
|
300
|
1900
2000
|
Answer: AC2=350, AC3=150,
BC3=300, BC4=200, CC1=700, CC2=200,
DC4=100 Total Cost= 15,250
Q4. A cement factory manager is considering
the least way transport cement from his three manufacturing centers P, Q & R to depots A, B, C, D & E. The weekly production
and demands along with transportation costs are given below. Apply stepping stone method.
|
A
|
B
|
C
|
D
|
E
|
Supply
|
P
|
4
|
1
|
3
|
4
|
4
|
60
|
Q
|
2
|
3
|
2
|
2
|
3
|
35
|
R
|
3
|
5
|
2
|
4
|
4
|
40
|
Demand
|
22
|
45
|
20
|
18
|
30
|
135
|
Answer: PB=45, PE=15, QA=2, QD=18,
QE=15, RA=20, RC=20, Total Cost =290
Q5. Consider the following transportation
problem and solve by applying VAM &
test it optimality. Apply stepping stone method
|
X
|
Y
|
Z
|
Supply
|
A
|
4
|
3
|
2
|
10
|
B
|
5
|
6
|
1
|
8
|
C
|
6
|
4
|
3
|
5
|
D
|
3
|
5
|
4
|
6
|
Demand
|
7
|
12
|
5
|
|
Answer: Total Cost =66
Q6. Given below is a table. Solve it as
transportation problems & test it optimality. Apply VAM and stepping stone
method
Factories
|
|
Centers
|
||||
1
|
2
|
3
|
|
Supply
|
||
P
|
16
|
19
|
12
|
|
14
|
|
Q
|
22
|
13
|
19
|
|
16
|
|
R
|
14
|
28
|
8
|
|
12
|
|
Demand
|
10
|
15
|
17
|
|
1900
2000
|
Answer: P1=9, P3=5, Q1=1, Q2=15, R3=12 Total Cost= 517
Q7. Given below is a table. Solve it as
transportation problems & test it optimality. Apply NWCM and stepping stone
method
|
W1
|
W2
|
W3
|
W4
|
Supply
|
F1
|
21
|
16
|
25
|
13
|
11
|
F2
|
17
|
18
|
14
|
23
|
13
|
F3
|
32
|
27
|
18
|
41
|
19
|
Demand
|
6
|
10
|
12
|
15
|
43
|
Answer: F1W4=11, F2W1=6, F2W2=3,
F2W4=4, F3W2=7, F3W3=12 Total
Cost= 796